Preferences
on the table

What fiscal indulgences the city offers to residents of the Technopolis Moscow special economic zone and how the desired status can be obtained.
Tax preferences for Technopolis Moscow SEZ residents
Tax preferences for Technopolis Moscow SEZ residents

0% VAT on imported goods*

  • Goods and equipment imported into the Technopolis Moscow SEZ are exempt from customs duties, taxes and charges.
  • The current customs station for innovative products allows for a reduction in customs procedures.
*When the customs clearance zone is set up at the resident's site

Requirements for a potential resident

  • No branches and subdivisions registered outside the Technopolis Moscow SEZ.
  • Technology development or industrial production.
FEASIBILITY INDICATORS
  • Investments per 1 sq. m over five years - from RUB 50,000.
  • Annual revenue per 1 sq. m - from RUB 200,000.
  • The average monthly remuneration shall not be lower than the one set by the Moscow Government (in 2020 - from RUB 68,176, subject to annual increment).
  • Investment per 1 ha over five years - at least RUB 250 m.
  • Annual revenue per 1 ha - at least RUB 300 m.
  • The average monthly remuneration shall not be lower than the one set by the Moscow Government (in 2020 - from RUB 68,176, subject to annual increment).
Stages and timeline for obtaining resident status
Submission of application on the Technopolis Moscow SEZ the website in the Investors section or via the investmoscow.ru portal
1
Selection of vacant spaces
2
Submission of application and business plan to the Moscow Department of Investment and Industrial Policy
3
15 working days - evaluation of the application and submitted documents
4
40 working days - meeting of the supervisory board and the interdepartmental commission (IDC)
5
5 working days from the date of the IDC decision - sending an extract with the IDC decision to the applicant
6
10 working days from the date of the IDC decision - sending a draft agreement to the applicant
7
Up to 10 working days - signing of the agreement by the applicant
8
2 working days - conclusion of a trilateral agreement (Moscow Department of Investment and Industrial Policy, Technopolis Moscow SEZ, applicant)
9
3 working days - the Moscow Department of Investment and Industrial Policy shall send a copy of the agreement to the Russian Ministry of Economic Development for including in the register and issuing the certificate
10
THE WHOLE PROCEDURE TAKES ABOUT THREE MONTHS
E-mail: pressprom@mos.ru
Audience: 16+